The changes
Policy W1 of the new NPPF, under section 10 is titled, ‘Securing clean energy and water’, specifically stating that emerging local plans should be informed by engagement with utility providers, regulators and network operators. This is to ensure that decisions on the allocation of land in development plans are informed by an understanding of energy supply and network capacity. The policy also states that decisions should consider the impact of planned growth, as well as the implementation of strategic infrastructure plans, such as Regional Energy Strategic Plans (RESPs).
The increased emphasis on energy supply within the NPPF will focus the attention of both councils and planning inspectors on the topic when assessing the suitability and deliverability of potential sites for allocation in a local plan. The additional focus will make these potentially determinative issues when choosing sites that may be in competition with each other.